Key Points

Paid pre-construction ends with a fixed-price construction contract, after hard bids for every line item and a Gantt chart (the schedule for the whole job) built around the subcontractors' availability.
A project manager oversees the superintendents, who run the work on site and manage the subcontractors.
Any change to the plans or the specifications is a change order, which can move the schedule and price.

You’re building your dream home, which can take a year to 18 months. Before you sign anything, it helps to know who runs the job, how the price and schedule get set, and what happens when plans change.

You’ll learn:

  • How a build starts
  • Why the architect and builder work together early
  • What gets decided in paid pre-construction
  • How we plan for a steep or tight lot
  • Who runs the job site
  • What happens when something changes
  • What happens after you move in

How Does a Luxury Build Start?

You may not know yet whether we’re the right builder for your project, and we may not be the right one for you.

So we start with a call about your project details, budget range, scope, and timeline. At the start of that call, we ask if you’re okay with telling us by the end of it that we’re not a good fit, and we’ll do the same. If your project isn’t something we do, we tell you and refer you to someone else.

If it’s a fit, we set up a site meeting and give you a preliminary ballpark price. Once you accept the preliminary pricing, we sign a professional service agreement, which starts our paid pre-construction phase.

You can see the steps in order on our custom home building process page.

Why Should the Architect and Builder Work Together Before the Design Is Final?

If the plans go to permit before anyone prices them, you can find out the design is way too expensive. Ideally, we get involved while your architect is still developing the plans, so we can help with pricing.

Two men reviewing a large set of plans on a garden path

Most architects do a good job on plans and details, but none of it is 100% fleshed out, so we go through the plans closely and ask the right questions at the right time. If we catch a question 2 months before that part of the work comes up, we have time to plan for it, so it doesn’t hold up the schedule.

Your architect does the design, since we don’t do design-build. We almost never change your architect’s design. We look for anything that’s missing, give feedback, and offer options. We also give a lot of feedback on how things get built, because a plan doesn’t always show that.

Our post on architect and builder collaboration digs deeper into the relationship.

What Gets Decided During Paid Pre-Construction?

We charge for the professional service agreement so we can do a lot of the upfront work. 2 things come out of it: the price and the schedule.

The Price

We get hard bids from subcontractors and vendors for every line item, and we resolve conflicts in the plans that need more detail. By the end, we can sign a construction contract with a fixed price built from those bids. We honor whatever is in the plans and the contract, even if we missed something.

The Schedule

We also build the Gantt chart (the schedule for the whole job) and talk to the subcontractors about their availability and how long each part will take. Then we work backward from the chart to a spreadsheet we call decision, action, deadline. It lists things like when the cabinets and tile have to be ordered and when the plumbing fixtures have to be on site, so we can stay on schedule.

By then, we’ve often settled what we’ll order for items with long lead times. We don’t place those orders or pay vendors until the construction contract is signed.

How Do You Plan for a Steep or Tight Lot Before Work Starts?

Before we dig, the geotechnical engineer takes boring samples to see how competent the soil is. The structural engineer bases the plans on that, and we calculate how much we’ll excavate so we can tell the city.

Aerial view of a hillside lot being excavated beside a house with solar panels

We also figure out shoring (the temporary supports that hold back the hillside) and if there are any underground creeks in advance, because those can delay the build.

We also have to figure out what size excavator we can get up there. A machine that weighs 60,000 to 70,000 pounds and reaches 50 to 60 feet in length can excavate isn’t easy to get up a curvy hillside road. Walking it up slowly so we don’t damage the asphalt can take a full day. If we can’t get a machine up there, we’ll have to do the work by hand.

While we’re hauling dirt, we usually have 10 or 12 dump trucks running at once. So we find places down the hill where they can wait, and we make sure it isn’t trash day.

There are people’s lives at risk when you’re excavating. In California, Cal/OSHA requires a permit to construct an excavation 5 feet or deeper that anyone has to enter.

Who Is Responsible for What During Construction?

Wood framing going up on a hillside home above a concrete foundation

Our project manager oversees our superintendents, who run the work on site and manage the subcontractors. Our superintendents are the boots on the ground, and our own finish carpenters handle finish work, like wood paneling.

We hold the subcontractors to the prices they bid, and staying on top of them is a huge part of the job. Before a subcontractor can get paid, we need a license number, W-9, general liability insurance, and workers’ comp.

Our subcontracts also cover their warranty and cleaning up their debris.

What Happens When Something Changes During Construction?

Say you decide you want more tile on a wall, or a different tile, after the contract is signed. Any change to the plans or the specifications is a change order. Before we move forward, we walk you through your options and what each one does to the cost and timeline.

A change can ripple through the schedule. For example, if you add a window, we need to reframe. Then we have to push the plumber out a week, and if the plumber isn’t available that week, out another week.

We try to avoid change orders, but they still happen. If something comes up on site, we tell you, and by then we’ve already worked out how to fix it.

We’ve also written about how custom home builders avoid surprise change orders.

What Happens After You Move In?

Kitchen with wood cabinets, a pro range, and a blue banquette by the window

Every home we build has a 5-year warranty on craftsmanship. It covers the finishes you can see, plus built-ins, cabinetry, tile, and trim. We call it our 5-year concierge warranty.

When you notice something, you log it in the shared warranty spreadsheet we give you at the end of the project. One of our warranty team members visits your home to review the list and make the repairs.

At the end of the project, we also hold a housewarming and give you a personalized photo album.

Ready to Plan Your Luxury Home Build With Vought Construction?

If you’re comparing builders, we’d be glad to talk through how we’d manage your project. See how our custom home building works, then fill out our contact form or give us a call.

Frequently Asked Questions

What does your pre-construction process look like?

It starts when you sign a professional service agreement, the paid phase before your construction contract. During it, we get hard bids from every subcontractor and vendor for each line item, work out any conflicts in the plans, and build the Gantt chart around the subcontractors' availability. Then we present a fixed-price construction contract.

What happens if I change something after the contract is signed?

Any change to the plans or the specifications is a change order, whether it's more tile on a wall or a different tile. Before anything moves forward, we go over your options with you and show what each one does to the cost and timeline. A change can ripple through the schedule, because trades like the plumber may have to move weeks.

How long does your warranty last?

Our craftsmanship warranty lasts 5 years. It covers visible finishes, built-ins, cabinetry, tile, and trim. You log what you notice in a shared spreadsheet, and a warranty team member reviews the list and does the repairs.