Say you drive by your lot once the work has started. You see a deep cut in the slope and gray concrete walls, but no house yet. That is how a hillside build looks in its first stage.
You’ll learn:
- What the stages of a hillside build are, in order
- What a steep lot needs before framing can begin
- How the foundation and steel go in
- Who keeps the schedule moving
- What to expect once the frame is up
What Are the Stages of a Hillside Build?

- Pre-construction. A geotechnical engineer takes boring samples to see how competent the soil is, and the structural engineer bases his plans on that. Before we dig, we figure out whether the job needs shoring and whether there are underground creeks, because both can really delay a job.
- Getting the excavator up the hill. If we can get a 60,000 to 70,000 pound machine with a 50 or 60 foot reach onto the lot, we can dig quickly. With a smaller machine, it takes a lot longer. Walking the excavator up the hill can take an entire day, with a team laying planks in front of it so it doesn’t damage the asphalt.
- Digging and hauling the dirt. Some excavations go 20 feet deep. We usually have 10 or 12 dump trucks running at once, and we can take out 50 loads a day if we have the access. On one East Bay Hills home, we hauled out about 1,200 yards of dirt.
- Holding back the slope. Houses here usually sit 5 feet from the property line, and we have to over-excavate, so we hold the hillside back with shotcrete or temporary piers.
- Pouring the foundation. On an East Bay Hills home, about 4 months passed between the vacant lot and the pour of the lower foundation walls.
- Setting the steel and framing. When a crane can’t get in, the steel comes up from the street below.
- Windows, doors, and finishes. This last stretch takes most of the time.
What Does a Steep Lot Need Before Framing Can Begin?
Approval comes first. The permits for an Oakland home took almost 2 years, with an appeal and a public hearing along the way. Once we had them, we brought in the excavator.

Then the dig starts. Sometimes we have to dig 20 feet down.

At that depth, the slope has to be held back while the crew works. Here, the dirt walls have been covered in shotcrete, which is concrete sprayed onto the soil over a grid of rebar.
We hold the hillside back with shotcrete or with temporary piers drilled into the ground. In these hills, we sometimes hit underground creeks too. Holding back the slope and running into creeks can both really delay a job, so we work them out in pre-construction, before the dig starts.
Our hillside construction challenges post covers more of what comes up on a slope.
How Do the Foundation and Steel Go In on a Steep Lot?

Pour day is a big moment. Right before it, a hillside site looks like the one in this photo: wood forms and rebar for the foundation walls, with a concrete hose running down to the work.
On that East Bay Hills home, the foundation crew worked for a couple of months before the day the bottom walls were poured. It was about 100 yards of concrete, with 10 trucks waiting to pump. The plan was to keep pouring until about 5 or 6 in the evening. Some of those walls are about 14 feet high and 12 inches thick.
Steel is its own stage. When a crane can’t get onto the lot, the steel has to come up from the street below.
Oakland’s building department says many construction projects need a special inspection under the California Building Code. The welding inspector, concrete testing, and other consultants sit outside our contract price.
Who Keeps a Hillside Build on Schedule Day to Day?
A construction schedule changes every week, so someone has to stay on top of it every day.
Our project manager does that. Each morning, the project manager calls our superintendents to ask what they need and which subcontractors need a push. In the afternoon, there’s a second call to ask what manpower they need tomorrow.
Our superintendents run the work on site and manage the subcontractors. Every Friday, we update the schedules in the office, but we keep the original schedule in place so we can see where we stand at any time.
The main thing we watch is the end date. Everything in between is likely to get moved around and adjusted.
What Should I Expect Once Construction Is Underway on a Hillside?

The early months move fast. In the beginning, a job usually runs ahead of schedule, because with the foundation and frame, you get 90% done in 10% of the time. Then the last 10% takes 90% of the time. That’s why we keep the original schedule as a fixed baseline, so a fast start doesn’t hide where the job really stands.
A few decisions will still be open. Most windows, doors, tile, and appliances get settled in pre-construction, before the construction contract. Smaller choices can wait, but they have order-by dates tied to the schedule. On one job, the interior door hardware still hadn’t been picked, so we settled it at the weekly meeting.
The house will also look different once you can stand in the rooms. A 2D drawing is one thing. Standing in the space, you may wonder why the fireplace mantel sits at that height, or decide a door should move 6 inches to the left.
Any change to the plans or specifications is a change order, like adding more tile to a wall or choosing a different tile spec. If a change adds an hour of labor, it adds a day because of how trades operate. We can’t say exactly how much time a change will add because it ripples through the trades.
Ready to Follow Your Hillside Build With Vought Construction?
If you have a steep lot, we’d be glad to look at it with you and talk through how a Vought Construction build would go. You can read more about our custom home building, then fill out our contact form or give us a call.