Key Points

The minimum is a standing weekly meeting with the homeowners and the project manager, usually with the architect too.
Dated photos of every room show what was inside a wall before the drywall covered it.
A choice worked out live in about 10 minutes can take 2 weeks over email.
The original schedule stays fixed and a working copy is updated every Friday, so it's clear how far ahead or behind the job is.
Out-of-town clients get the same agenda over Zoom and the same daily album.
Communication matters because the relationship runs a long time, from pre-construction through the build and the 5-year warranty.

How often are you supposed to hear from the people building your house? And when a week goes quiet, does that mean everything is fine, or that something went sideways behind a wall you can’t see anymore?

You’ll learn:

  • How often we are in touch during a build
  • What lands in your daily photo album
  • How the weekly site meeting runs
  • How the schedule gets updated between meetings
  • How all of it works if you live far from the site

How Often Will I Hear From My Builder?

Carpenter standing in the wood-framed attic of a home under construction beside a large window

The minimum on our custom home builds is a standing weekly meeting with you and our project manager, and usually your architect too. We also send a written update at the end of every week, by text or email, on what happened and what’s coming. On top of that, we text through the week and share photos daily, so you hear from us most days.

What Does a Daily Job-Site Photo Album Show Me?

Aerial view of a home with new wood framing next to a pool and trees

Every day we’re on site, our field team adds photos to a shared album for you. We tell them to go through every room and take lots of pictures.

The album gives you a dated record of the house at every stage, including the parts that get covered up. 10 pictures of the same wall can look like too many, until something happens in that wall. One of our albums has about 3,000 photos in it. Because the photos are dated, if something happens in a wall later, we can see exactly what it looked like on each date.

What Happens at the Weekly Site Meeting?

We start with our team’s questions from the job site, so they get answers fast. Then we go through the schedule, what has happened, what’s coming up, and any decision still waiting on an answer. We use the same agenda every week, and we walk through the house.

You, our project manager, and usually your architect are there. Your architect is your advocate and your eyes and ears on the job. We save up questions for the architect and bring them together before the meeting, so nobody gets a million emails. One client in Southern California comes up regularly for the field meetings, so there are more eyes on the job.

It’s one thing to see a plan on paper. It’s another to stand in the room and ask why the fireplace mantel is at that height, or see that a door should move 6 inches to the left. Our clients are building their dream home, so they want it right the first time.

Why Do We Make Selections During the Meeting?

Kitchen with a stone waterfall island and dark cabinets before the floors are finished

Because something that can be worked out in 10 minutes on a live call can take 2 weeks over email. Most choices, like windows, doors, tile, and appliances, are made during pre-construction. A few are still open when the build starts, like interior door hardware on one recent job. We ask you to pick those during the meeting.

Long-lead items are why most choices are made in pre-construction. Getting every detail of a window order right can take 1 to 2 months of back and forth between you, your architect, and the supplier. If a lead time gets missed, a single item can turn into 3 months of waiting.

How the decision gets madeHow long it can take
Worked out live10 minutes
Worked out over email2 weeks

How Does the Schedule Stay on Track Between Meetings?

We set up the schedule in JobTread and save the original version so it never changes. Every Friday, our team meets at the office and updates a working copy. Keeping the original version fixed lets us see where the job stands at any given time.

A construction schedule isn’t set in stone. The date that matters most is the end date. Everything in between is probably going to get moved around and adjusted, which is why we review it every week. A change order with labor in it can move the schedule, since an extra hour of work can add a day. A material swap on its own doesn’t usually change it.

The city has a say in timing as well. In Berkeley, you may need an inspection while the work is in progress, and a final inspection when it’s complete.

Between meetings, our project manager and assistant project manager call the superintendents in the morning to see what they need and which subcontractors to follow up with. In the afternoon, they check how many workers each site needs tomorrow. That way we’re in touch with every crew on the job every day.

How Does This Work if I Live Out of State or Overseas?

Hillside home under construction wrapped in scaffolding at sunset

The weekly meeting becomes a Zoom meeting, with the same agenda and the job-site questions first. For one of our overseas clients, we also have the architect come to the site. The daily photos go into the same shared album, and you can comment on them.

We have out-of-town clients right now, one in London and one in Seattle.

Why Does Regular Reporting Matter So Much?

Pre-construction can take about 6 months to a year, the build runs about 12 to 18 months after that, and our warranty runs 5 years. That’s a long time to work with people, and you shouldn’t have to guess what they’re doing. If you want a closer look at how long a custom home takes to build in the Bay Area, we’ve written that up too.

StageUsual length
Pre-constructionabout 6 months to a year
Constructionabout 12 to 18 months
Warranty5 years

In any relationship, how well and how often you talk is one of the biggest things, and a build is a long relationship. Good builders all do quality work, so what sets a builder apart is the experience, and communication is a big part of that. We tell clients up front that either of us can bow out if the fit is wrong, because we’re going into a marriage of sorts, from pre-construction through the 5-year warranty.

So we’re upfront and honest, and if something goes wrong, we never hide it. We’re usually the first to admit when we made a mistake. Owning our mistakes is a big part of how we earn trust.

Want to See How Updates Would Work on Your Project?

If you’re weighing builders, ask each one how often you’ll hear from them. We’re happy to show you how a custom build runs at Vought, or you can start with our custom home building in Berkeley.

Frequently Asked Questions

Who is my day-to-day contact during the build?

Your project manager is your day-to-day contact for communication, scheduling, and logistics. Jorge Escobedo, our co-owner and managing director, handles estimating, client submittals, and architectural oversight.

Do you keep my neighbors informed?

Yes, during the build. Nowadays we typically ask you to put together a group email for the neighbors, so we can keep them updated, for example when concrete is coming and we need parking. Sometimes we meet neighbors face to face, introduce ourselves, and let them know they can call us. We wrap the fencing and the portable toilets, and we keep the mess inside the site.

Do the updates stop when the build is finished?

No. At closeout, you get access to a shared warranty spreadsheet where you log anything you notice over time. One of our warranty team members visits every 3 months for 5 years to go over the list and make the repairs.